Value
|
Formula
|
Purpose
|
cost variance (CV)
|
EV
- AC = CV
|
CV provides the cost performance of the
project to help determine whether the project is proceeding as planned.
|
schedule variance (SV)
|
EV
- PV = SV
|
SV indicates the project's schedule
performance. This value can indicate whether the project work is proceeding
as planned.
|
cost performance index (CPI)
|
EV
/ AC = CPI
|
For a cumulative CPI, divide the sum of
all earned value (EV) budgets by the sum of all actual costs (ACs). A CPI of
less than one indicates that the project is over budget, and a CPI of over
one indicates that the project is coming in under the estimated budget.
|
schedule performance index (SPI)
|
EV
/ PV = SPI
|
Project managers can use the SPI to help
predict when their projects will be completed. An SPI of one indicates the
project is on schedule; greater than one indicates it is ahead of schedule;
and less than one indicates it is behind schedule.
|
estimate at completion (EAC)
|
AC
+ ETC = EAC
|
EAC is used by project managers to give
their best estimate of the total costs of projects based on actual costs to
date. There are three formulas associated with this value. This formula is
typically used when previous assumptions regarding costs are wrong.
|
estimate at completion (EAC)
|
AC
+ BAC – EV = EAC
|
Use this formula when variances are not
expected to occur again. Budget at completion (BAC) is the total planned
value (PV) at completion.
|
estimate at completion (EAC)
|
AC
+ ((BAC – EV) / CPI) = EAC
|
This formula is used to calculate the EAC
when variances are likely to recur.
|
ETC
|
N/A
|
This ETC is not a calculated value based
on any formula. Instead it is provided by the performing organization for use
in the formula AC + ETC = EAC when previous cost estimates are wrong. The
situations where atypical and typical variances are considered do not apply
in this case.
|
estimate to complete (ETC)
|
BAC
- EV = ETC
|
ETC can help project managers in
forecasting what the final cost to finish the project may be. Two formulas
are used to calculate this value. This formula is applied when variances are
not expected to occur again.
|
estimate to complete (ETC)
|
(BAC
- EV) / CPI = ETC
|
Use this formula to calculate the ETC for
when variances are likely to recur.
|
9 Ağustos 2012 Perşembe
Performance Measurement Analysis and Forecasting
Kaydol:
Kayıt Yorumları (Atom)
Hiç yorum yok:
Yorum Gönder