Cost Baseline Example


Cost Baseline

Work Package

Due Date

Cost

Contingency Reserves

Total

Laptop Acquisition
02/01/05
$450,000
$22,500
$472,500
Laptop Configuration
02/25/05
$67,000
$3,350
$70,350

Laptops Complete

02/25/05

$517,000

$25,850

$542,850

Redesigning Internal Software
01/05/05
$48,000
$2,400
$50,400
Acquisitions and Infrastructure Upgrades
01/15/05
$134,000
$6,700
$140,700
Installing and Configuring VPN Server
01/20/05
$35,000
$1,750
$36,750

VPN Server and Internet Connection Complete

01/20/05

$217,000

$10,850

$227,850

Testing Laptops, Servers, and Connections
04/01/05
$10,000
$500
$10,500

Testing Complete

04/01/05

$10,000

$500

$10,500

Training Program
05/15/05
$25,000
$1,250
$26,250

Training Complete

05/15/05

$25,000

$1,250

$26,250

TOTAL BUDGET


$769,000

$38,450

$807,450