Performing a Critical Path Method analysis on a project network diagram reveals the earliest and latest possible start and finish dates for each activity and the overall duration of the project. But what happens if the calculated dates don't fit within the project deadline? You can apply the results of your Critical Path Method analysis to help find the best way to reduce the overall duration of the project.
1) Crashing:
- Identify
the critical path through the network diagram.
- Are there
activities on the critical path that occur when no other work activities
are being performed at the same time? Can the duration of these activities
be reduced by applying more resources? What would be the cost of
additional resources? Would reducing the duration of the activity result
in cost savings such as reduced overhead or penalties? If the savings
generated by applying more resources are greater than the cost and
additional resources are available, the estimated duration can be reduced.
- Identify
activities on the critical path that are performed simultaneously with
activities that are not on the critical path. How much float, or slack
time, is included in the noncritical path for the simultaneous activity?
Can the duration of the activity on the critical path be reduced by the
amount of float? What are the associated costs and savings? If the savings
outweigh the costs, you may reduce the duration of the activity on the
critical path.
- After you
have identified all the available opportunities to shorten the critical
path, perform a new Critical Path Method analysis using the revised
duration for all activities. The critical path may change as a result of
your revisions.
- Identify
the critical path through the network diagram.
- Reexamine
the dependencies shown among activities on the critical path. Are there
any activities that can begin before preceding activities have been
completed? If so, the dependencies shown in the network diagram can
change.
- Can the
later activity begin at the same time as the earlier activity? Are there
sufficient resources available to perform both activities simultaneously?
If so, a parallel path may be created for the later activity. It can be
moved off the critical path.
- Can the
later activity begin after the earlier activity has begun but before it
finishes? Are there sufficient resources available to perform both
activities simultaneously? If so, revise the start date shown on the later
activity. Using the estimated duration, recalculate the estimated finish
date.
- When you
have identified all the opportunities to fast-track activities on the
critical path, perform a new Critical Path Method analysis of the project
network diagram. The critical path may change as a result of
fast-tracking.
Hiç yorum yok:
Yorum Gönder